Overview
Boothferry Bridge is an historic crossing over the River Ouse, near Howden, in East Yorkshire.
It opened in 1929 to replace a centuries-old ferry service that had operated since at least 1513. The bridge was built to improve transport links between the north and south banks of the Humber, cutting 25 miles off the journey from Hull to London. At the time of its opening, it was the furthest downstream crossing of the Ouse and played a vital role in regional connectivity until the M62 Ouse Bridge opened in 1976.
In 2021, the bridge underwent a major refurbishment to extend its lifespan and improve safety. Mason Clark Associates (MCA) supported East Riding of Yorkshire Council (ERYC) by providing engineering consultancy and tender evaluation throughout the project.
Challenges and Solutions
Refurbishing Boothferry Bridge came with a unique set of challenges due to its age, structure, and location. We worked closely with ERYC and the contractor to overcome these issues efficiently.
To undertake the works, various permissions were required from the Canal and River Trust, Marine Management Organisation, Natural England and Trinity House.
Challenges were addressed by:
These solutions helped keep the project on track and ensured the bridge was refurbished to a high standard.
MCA's Contribution
We provided end-to-end engineering support throughout the project, carrying out detailed inspections in line with current standards, helping to identify structural issues early and recommend practical solutions. Our team’s contribution included:
Our collaborative approach helped the client manage risks and control costs.
Results
The Boothferry Bridge refurbishment was successfully delivered, despite some unexpected delays. In June 2022 the works were temporarily suspended due to severe traffic congestion caused by overlapping roadworks on the nearby M62 Ouse Bridge.
To minimise disruption to the public, the bridge was reopened to two-way traffic while construction was paused.
The refurbishment resumed in July 2022, and remaining works were completed, albeit with a reduced scope, while maintaining traffic flow.
Key outcomes included:
The project has extended the bridge’s lifespan and improved safety, ensuring it remains a vital transport link for the region.